6/29 Groundbreaking Ceremony! 7/20 Foundation block laid.7/20 Foundation block laid.7/25 Rough-in underground plumbing. Start prep for concrete slab.7/26 Concrete slab poured.7/26 Concrete slab poured. Layout for walls begins.7/31 Exterior wall layout and interior wall layout. Framing begins.8/11 Trusses delivered and installed. Roof install begins.8/19 Finished framing/sheeted roof. Set exterior doors and windows.8/20 Siding and fascia install completed. Rear view of building.8/20 Siding and fascia install completed. Rear view of building.8/20 Siding and fascia install. Front entrance of building.9/20 Blessing Ceremony: Staff and their families wrote encouraging notes on the cement before flooring was laid.9/20 Blessing Ceremony: Staff and their families wrote encouraging notes on the cement before flooring was laid.9/20 Blessing Ceremony: Staff and their families wrote encouraging notes on the cement before flooring was laid.9/20 Blessing Ceremony: Staff and their families wrote encouraging notes on the cement before flooring was laid.